To create a Cost Rate:
Expand WBS by clicking on the
...
arrow .
Expand Cost Rate Setup by clicking on the
...
arrow
Click on Cost Rate
...
Cost Rate* - Select an option from the menu that fits the Cost Rate being set up:
Cost Rate By Employee, WBS Level 1
Cost Rate on Employee, Time Code and WBS Level 1
Select Add
In the New Cost Rate setup screen select the following fields.
Cost Code* - Select a
...
cost code to indicate what components will drive the rate. Depending on the type of bill code selected the additional fields in the window will vary
Effective Date*: Enter the date this report will take effect.
...
Time Code* - Select a
...
time code that is already set up from the drop down menu where the rate will apply.
WBS Level
...
1* - Select a
...
project that is already set up from the drop down menu where the rate will apply.
...
WBS Level 2* - Select a
...
Department* - Select a department that is already set up from the drop down menu where the rate will apply.
...
Time Code* - Select a time code that is already set up from the drop down menu where the rate will apply.
...
task that is already set up from the drop down menu where the rate will apply.
Employee * - Select an Employee
Currency* - Select the currency in which the rate will apply
Cost Rate* - Enter in the rate
Click the Save
* Indicates a required field
...