Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

To create a Cost Rate:

  1. Expand WBS by clicking on the

...

  1. arrow image-20240531-145334.pngImage Added .

  2. Expand Cost Rate Setup by clicking on the

...

  1. arrow image-20240531-145347.pngImage Added

  2. Click on Cost Rate

  3. Select Add

  4. In the New Cost Rate setup screen select the following fields.

    • Cost Code- Select

...

  1. Cost Rate By Employee, WBS Level 1

  2. Cost Rate on Employee, Time Code and WBS Level 1

...

    • a cost code to indicate what components will drive the rate. Depending on the type of bill code selected the additional fields in the window will vary

    • Effective Date*: Enter the date this report will take effect.

    • Time Code* - Select a time code that is already set up from the drop down menu where the rate will apply.

...

Effective Date*: Enter the date this report will take effect.

    • WBS Level 1* - Select a project that is already set up from the drop down menu where the rate will apply.

    • WBS Level 2* - Select a

...

    • task that is already set up from the drop down menu where the rate will apply.

    • Employee * - Select an Employee 

    • Currency* - Select the currency in which the rate will apply

    • Cost Rate* - Enter in the rate 

  1. Click the Save 

* Indicates a required field

Required fields will vary depending on the Cost Rate Selected